Dear all,
A short update.
I worked on the set up of the
budget and uploaded it in the restricted area (and attached). It contains:
- "Top-down" sheet with rough allocations among WPs
- “PMs Personnel costs” sheet. You can “play” with PMs allocation and all figures will be updated automatically
- “Travel costs” sheet with estimates of travel costs per partners
- “Other costs” sheet (empty so far)
- “Detailed budget” and “Summary table” sheets with a summary of the previous sheets.
I set up also the GANTT chart (attached and on box) with the tasks defined so far. Please note that WP1 currently contains a task dealing with ethical issues. In case we decide to keep WP2 Ethics we
must adjust the WP1 description accordingly
Best regards,
Loredana